Scope:
Upgrade/refurbishment of fourteen hypochlorite dosing plants comprising: |
- Removal of the existing ABB PLCs and Secomea Site Manager units (used for remote control by a third-party Contractor who operate the chlorinators on YVW’s behalf).
- Installation of a new Brodersen RTUs, Garderos modems and Fernhill HMI solution.
- Installation of new ProMinent Post Dose Chlorine Analysers.
- Part supply and full installation of a new pre-dose chlorine analyser system in new free standing cubicle (at specified sites only).
- Includes installation of associated sample and return lines.
- Ancillary works.
Achievements/Outcomes:
Use of appropriately skilled Jonoco technicians to ensure minimal downtime on the operation of the plants.